Forecasting Future Performance Trends

The Schedule Performance and Cost Performance Indices not only monitor current project performance, they can also be used to predict future performance trends.

  • To-Complete Performance Index (TCPI) = (BAC-EV) / (BAC-AC). Indicates the CPI required throughout the remainder of the project to stay within the stated budget.

  • Estimate at Completion (EAC) = AC + ((BAC-EV)/CPI). A forecast of total costs that will be accrued by project completion based on past cost performance trends.

  • Variance at Completion (VAC) = BAC - EAC. The difference between the new Estimate at Completion and the original Budget at Completion.
     
Earned Value Perfomance Review

For further reading, try this free Earned Value Management eBook:

Successfully Presenting Earned Value is a free e-book which will help you learn to implement and present Earned Value schedules.  It offers both an explanation of Earned Value Management principles, and step-by-step instructions.  This e-book is offered at no charge.  After reviewing it, you may be interested in downloading our Milestones Professional software.  Milestones Professional was used to produce the presentation-ready Earned Value reports shown in the e-book and can be used to make schedules in many formats, including Gantt charts, Milestone charts, Summary charts, Resource Charts and more. 